Location: The project runs along Wall Rd from Moontown Rd to Brownsboro Rd. The total project length is about 0.7 miles.
Project Description: The project includes the installation of 3700 feet of new PVC pipe to replace existing mains as well as installation of new fire hydrants. Customer water services will be transferred to the new main, once installed. Repairs to roadway surfaces, driveways, and landscaping will be completed as the project progresses and after the bulk of the water main installation is complete. There may be temporary impacts to traffic routing due to lane closures as the work progresses.
Project Timeline: This project is complete and is now in the warranty stage.
Need for Project: This project replaces aging water main along Wall Rd that has seen numerous main breaks in recent years.
Questions: If you have any issues related to this project, please call (256)746-2888.