Location: The project runs along Butler Rd from Henry Taylor Rd to Joe Quick Rd. The total project length is about 1.1 miles.

Project Description: The project includes the installation of 5600 ft of new PVC pipe to replace existing mains. Customer water services will be transferred to the new main, once installed. Repairs to roadway surfaces, driveways, and landscaping will be completed as the project progresses and after the bulk of the water main installation is complete. There may be temporary impacts to traffic routing due to lane closures as the work progresses.

Project Timeline: This project is currently under construction and should be completed October 2025. 

Need for Project: This project replaces aging water main along Butler Rd that has seen numerous main breaks in recent years.

Questions: For any additional questions on this project call Vince Moody (256)783-1547 (7AM-3:30PM) or email at vmoody@madisoncountyal.gov.